Critical path-Longhest path
In the Open Standard
Rachel DorotaMember for 12 years 10 months
- Created
- 3
- 2
0
Dear all,
In P6 critical activities are defined by either the total float or the longhest path. I set up a program in P6 ver7.2 and when I calculate the critical path using the Longest Path filter, the result is an empty page, meaning no activities in longest path. Why is this happening? Should I change some settings? Is it normal not to have a longest path in a project? (If it is normal how can it be justified and what does it say about the project?)
regards
3 replies
Oldest firstLog in or join to reply