Delayed Critical activity with no negative float
In the Open Standard
Mahmoud AbohashemMember for 13 years 9 months
- Created
- 2
- 1
0
I have some critical activities (total float=0) are delayed by 27 days during updating, but it gives me only (-9) of total float
while it should be (-27)
for example it is to be finished according to BL at 1st of December 2013, according to update it delayed to be 27th of December 2013, and its baseline total float is zero, now it is giving me (-9) days of total float
the project finish date is constrained (must finish by)
this problem occured when i imported the update in another version of the baseline
any help is appreciated