Skip to content

Progressin activities with Data Line Issues

Charlie DanielsMember for 12 years 10 months
Created
0
3
0

Hi,

 

1. When I use the data line to update my activities, it automatically completes certain tasks which should still be in progress?

2. Once some activities have been progressed, I F9 and some of the increase in duration?

3. If I manually select a task 'Start' or Finish then the successor will fall back to the data line?

 

I have a really large schedule and these occurrunces are making it hard for me to manage the schedule.

 

Please any help?

 

Thanks

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?