contractual Problem
In the Open Standard
Moutaz AldeibMember for 22 years 9 months
- Created
- 2
- 3
0
Dear Engineers,
My project has not commenced contractually as the Advanced Payment and LC have not been received and opened, however the owner asked us to start constructing the site which was actually started and nearly completed, now I am going to establish a baseline schedule but I do not know where to include the site preparation, shall I include it before the start date of the project which is the real situation or is there another trick I can do to manage this problem?
Regards,
Moutaz