Assigning Contractual Payments
- Created
- 5
- 2
Hi there all,
In P6, I'm trying to assign the contractual payments of a purchased equipment but I could not find a satisfactory way to represent the situation. Let's say, I am planning to purcha an eqp. A which has the following activities according to the schedule:
A1000- Collection of Proposals
A1010- Evaluation of Proposals
A1020- Contract Negotiations
A1030- Contract Signing (as a milestone)
A1040- Delivery to Site
Plus, I have the following payments for the eqp.
P1: 1st Payment in May (may be an advance payment)
(NO PAYMENT IN JUNE)
P2: 2nd Payment in July
P3: 3rd Payment in August
(NO PAYMENT IN SEPTEMBER)
(NO PAYMENT IN OCTOBER)
P4: 4th Payment in November
As can be seen, there is an irregular distribution o payments which prevents me to assign all of them using expenses over activities as the expenses are assigned either at the start of activity/end of activity/uniform over the activity.
I decided to create a milestone activity for each payment (say A2000-Payment 1) under a WBS level named "Payments" and adjust the relationship with lags so that the activity date coincides with my payment periods. But that comes out to be an overburden since I have around a hundred equipments to be purchased.
Is there an easier or practical way that I can handle those kind of contractual payment costs?
Thanks in advance.
Regards.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?

