Skip to content

Problem in material resource budgeted units after importing xer file

Yaser A. Al-BustanjiMember for 16 years 5 months
Created
5
4
0

Hi Everyone, 

i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?

unit price is not zero and calculate cost from units is checked

Best regards,

5 replies

Oldest first
  1. 0
    Casey F ·

    I am having the same issue.

    I am having the same issue. I loose the budget units when importing, but not consistently. About a quarter of the resources maintain their budgeted units. I am running 17.8 exporting as 8.2 per customer requirements.
  2. 0
    Zoltan Palffy ·

    uncheck calculate costs from

    uncheck calculate costs from units 

  3. 0
    Kari Lucas ·

    I'm having the same issue.

    I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.

  4. 0
    Zoltan Palffy ·

    also check your duration type

    also check your duration type make sure it is set to fixed duration & units/time for each activity 

  5. 0
    Mk Tse ·

    What setting (resource and

    What setting (resource and cost related fields) is selected on Import template?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?