Cost Loading Activities
- Created
- 4
- 3
Hi Planners,
Just wondering if someone can help me cost load a 'warehouse rental' activity in my P6 programme.
I've got a 'Level of Effort' activity which reflects the duration of warehouse rental requred.
I've set the duration type to 'Fixed Units/Time'.
I've tried playing with all sorts of combinations of assigning a monthly (or weekly/daily - whatever) 'rental' expense cost, but I can't get it to multiply out by the activity duration.
Should I be doing it via resources instead?
If someone could show me how, I'd appreciate it a lot.
Surely it's simple to do, right? It's a pretty common thing to have costs that are dependent on the activity's duration.
Thanks,
Hugh.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?