Leveling resources: "Activities that cannot be leveled". Why

Håkon HaukebøeMember for 14 years 1 month
Created
3
3
0

Hi. I'm doing a feasability analysis for an early fase project. I'm trying to build different scenarios with respects to resources and time. I have around 100 activites. I've set Original Duration and Budgeted Labour units. When i use Shift+F9 i still get over-allocated resources. In the schedlog.txt - 4 activites are listed as "Activites that cannot be leveled". I see no reason why they cannot be leveled. Any clues?

 

Cheers

 

Haakon

3 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    One potential reason: if the

    One potential reason: if the number of assigned resources exceeds the number of available resources.

    I cannot imagine other reasons without looking at your project. If you will delete confidential information (usually costs) and will upload xer file at some file exchange site we may look at it to find the source of your problem.

  2. 0
    William Chee ·

    make sure your budgeted

    make sure your budgeted units/time is lower or equal to max units/time.

  3. 0
    Håkon Haukebøe ·

    Thank you guys. William, spot

    Thank you guys. William, spot on! Rounding error led to marginal overallocation.

     

    Cheers

     

    Haakon