Use Performance factor to calculate Hours to Spread in Histogram
In the Open Standard
Katie CoombsMember for 13 years 3 months
- Created
- 0
- 3
0
Hello,
I am trying to incorporate a productivity factor to my hours to finish the project to show an accurate spread of hours/resources needed in Histograms. However i don't want to change my remaining to earn hours (for S-Curves). Ideally i would like to use the ETC that is calculated using a PF factor, but I can't get the ETC hours to spread in a time distributed report. Does anyone have any suggestions on how I can achieve this?
Thanks in advance.
K
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?