Skip to content

Budget Cost Loaded

Moutaz AldeibMember for 22 years 9 months
Created
0
4
0

Dear Planners,

I assigned resourses to the activities, some of the assigned resources I loaded with Budget Cost, but after I changed the duration of those activities and the activity calendar, I detected that some of the assigned resources are not loaded with the budget cost I loaded. I tried to find the error but I could not.

Regards,

Moutaz

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?