P6 resource assignments
In the Open Standard
Derrick McInnesMember for 12 years 8 months
- Created
- 4
- 2
0
Im having some trouble. I have task scheduled for lets say Oct 24 2013-June 15 2013. In the resource asssignments its showing dates like January 6 2014-Jul 2016? I have checked the resources and they are scheduled Oct 24 2013-June 15 2013 as well. I know if I changed the org duration I can get it closer to the June 15 2013 date but that still doesnt solve it starting earlier as I cant get it to budge from the Jan 6 start. Thanks so much I am having a hard time
4 replies