Integrating P6 with other programs

Zach StarostkaMember for 12 years 8 months
Created
1
6
0

Hello Everyone,

I have a question that I don't know if it can be answered or not.  

Our company has really ramped up the size of our projects and they are run with all sorts of different programs mainly HeavyBid, Sage Timberline, and P6.  

I was wondering in there a way to make all of these programs talk to each other so we can smoothly run our new operations?  I HeavyBid can talk to P6 a little bit but Timberline on the other hand I'm not so sure.

Does anyone have any insight on this?  If so please let me know any questions comments or answers are welcome!

 

Thanks

1 reply

Oldest first
  1. 0
    Manochehr Hosseini ·

    Dear Zach, the answer is

    Dear Zach,

     

    the answer is yes.

    there are to way to do that:

    1- via PMSDK and using ODBC in windows

    2- Via API

     

    Both needs programing, if you want more information drop an email to my email address use private message service

    Regards,

    Manochehr