P6 - Remaining duration does not change when Original Duration is altered.

Jonathan JayMember for 12 years 8 months
Created
4
2
0

I have imported a schedule from MS Project to P6 v.7.0. I changed all of the activity types from "resource dependent" to "task dependent" and I changed the duration type from "fixed duration and units" to "fixed duration and units/time".

Now when I change an un-statused activity's original duration in P6, the remaining duration doesn't change. It appears that the link between OD and RD is turned off. Can someone tell me where I can reset this link? I can change each duration individually, but I'm curious as to why the RD doesn't change automatically.

4 replies

Oldest first
  1. 0
    Manochehr Hosseini ·

    DEar Jonathan,There is no

    DEar Jonathan,

    There is no link between OD and RD unless the activitiy doesnt have any actual.

     

    Regards,

  2. 0
    mani M.R ·

    Hai Jay Please check the

    Hai Jay

     

    Please check the below option

     

    Project - Calaculation Tab - Link Budget and at acompletion for not started activities (Ticked) 

                                          Reset Remaining duartion & Units to Original (Enable)

     

    Regards

    Mani

  3. 0
    Mazura Maarof ·

    thanks..helpfull!

    thanks..helpfull!

  4. 0
    Mazura Maarof ·

    unfortunately it does when u

    unfortunately it does when u importing ms project into P6. i was wondering why my finish date doesnt move after i change the OD. End up, i find out the RD was different from OD eventho wtihout actual. 