P6 - Remaining duration does not change when Original Duration is altered.
In the Open Standard
Jonathan JayMember for 12 years 8 months
- Created
- 4
- 2
0
I have imported a schedule from MS Project to P6 v.7.0. I changed all of the activity types from "resource dependent" to "task dependent" and I changed the duration type from "fixed duration and units" to "fixed duration and units/time".
Now when I change an un-statused activity's original duration in P6, the remaining duration doesn't change. It appears that the link between OD and RD is turned off. Can someone tell me where I can reset this link? I can change each duration individually, but I'm curious as to why the RD doesn't change automatically.
4 replies
Oldest firstLog in or join to reply