Ghost Activities and Users

Alan ChadwickMember for 23 years 3 months
Created
3
4
0

I have recently imported some XERs that have been created by other users, the problems are:

There are ghost constraints on activities, basically the asterisk * is in the finsh date field implying that there is a constraint, however on the activities status tab there is no constraint selected, this is causing a problem with float calculations.

Also if I simply try todelete teh project I am getting a messgae that says the project is inuse by other users....I am on a standalone version.

Does anyone know of any solutions to these, have looked in the various project and admin settings but have not found anything that willcure the problem.

Thanks

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi AlanMaybe you have

    Hi Alan

    Maybe you have imported a standalone programme that was once part of a group with cross programme links.

    Otherwise Spooky or what.

    Best regards

    Mike Testro

  2. 0
    Gary Whitehead ·

    Alan, As Mike says, this is

    Alan,

     

    As Mike says, this is probably due to an external relationship. If you add the colums "extertnal Early Start" and "external Early Finish", you should be able to find them.

    There is also an option in the scheduling window to ignore external relationships

     

    Can't help with your other query -never happened to me. Sounds like maybe the DB has got confused and didn't register you as having logged out of the project on a previous occaision. Sounds like one for Oracle support to me.

     

    Cheers,


    G

  3. 0
    Alan Chadwick ·

    Guys thanks for your

    Guys thanks for your responses.

    These programmes have been built as standalones but have been inter linked.

Log in or join to reply