Activity Suspension
In the Open Standard
Abilash Palakkadan MathewMember for 14 years 1 month
- Created
- 6
- 1
0
Hi guys,
In P6 8.1, I found something strange with activity suspension; when I have updated the schedule with DD – 14/Feb/14 I found one activity to be suspended from 28/Feb/14 till 15/Mar/14.
After entering the suspension and resume dates, when I reschedule the activity moves and it shows that the remaining job to be performed only after 15/Mar/14 onwards. It doesn’t shows the work to be performed between data date and suspension date (14/Feb/14 ~ 28/Feb14).
This is affecting the resource distribution as well; have any of you experienced this? Advise if you have any suggestions to fix / get rid-off this problem.
Regards,
Abilash