what mean ? Activities with unsatisfied relationships / Milestone Activities with invalid relationships

Young Tae OhMember for 12 years 7 months
Created
4
3
0

hi daer.

I am  a scheduler of primaver p6 , and I running sch botton, find log file .

log file was written " Activities with unsatisfied relationships  " " Milestone Activities with invalid relationships"

 

I want to know the detailed information , what mean ?

and Please, show me a example  of that  or explain  and video

 

thank for your kindly answer 

4 replies

Oldest first
  1. 0
    Dennis Hanks ·

    Ron:What you say makes sense,

    Ron:

    What you say makes sense, though in truth, I never thought about it.  However, I'm not getting any error message (Invalid Relationship) though I have several FS connections to a Finish Milestone.  I'm using P6 8.3.  Just curious.  Thanks.

  2. 0
    Ronald Winter ·

    Invalid Relationships are

     Invalid Relationships are relationships referring to parts of a milestone that are not there.  Does a Start Milestone have a finish date? NO, so it should not have a Finish-to-start successor relationship.  There is no finish date to ‘attach’ the relationship to.

     On the other hand, dies a Finish Milestone have a start date?  NO, so it should not have a Finish-to-start predecessor.  P6 will let you assign this relationships, but this report will flag them.

  3. 0
    Nick Jackson ·

    Here's an interesting point

    Here's an interesting point referring to Ron's reply. When you run your project through a QSRA, of course if you have too high % of SS or FF relatiionships (over 10%) it will be marked down. So effectively you are punished for having too many milestones.

  4. 0
    Zoltan Palffy ·

    Nick the type of

    Nick the type of relationships has mothing to do if its a milestone or not  

Log in or join to reply