Gantt chart separation of activities

Tyler WoodsMember for 13 years 11 months
Created
5
2
0

My project has several locations of work performed and I have them grouped by activity codes A,B,C... This does not appear to be enough separation for my customer.  Is there a way to insert a horizontal line to separate these activity groups?

5 replies

Oldest first
  1. 0
    Raymund de Laza ·

    I suggests to create a

    I suggests to create a different colored bar for each location.
  2. 0
    Gary Whitehead ·

    I don't think there's a way

    I don't think there's a way of creating a proper horizontal line, but you could insert a LOE activity at the top of each activity group, and give the bar a different colour.

    Or increase the row height of the 1st activity for each group.

  3. 0
    Mike Testro ·

    Hi RaymundHow do you put a

    Hi Raymund

    How do you put a different coloured bar on P6?

    Best regards

    Mike Testro

  4. 0
    Muhammad Anwar ·

    Mike,Create a filter to

    Mike,

    Create a filter to pickup these bars

    Then go to view - Bars and creat a new bar with desired color but in filter assign the created filter for those bars.

    Regards

     

    Muhammad

  5. 0
    Raymund de Laza ·

    Mike,On bar options there is

    Mike,

    On bar options there is filter as critical or nomal. The same can be applied as location 1, location 2 and so on. Need to assgn the activities with those activity codes such as location 1, location 2 an so on... create bar legends as the activity codes and filter accordingly.

     

    Regards,