Non-Labor Resource Assignment in Columns in a Layout

Pranab Kumar DebMember for 19 years 8 months
Created
2
2
0

Hello All,

I am using Primavera Project Management 6.1, I want to see Non-Labor Resource Assignment in Columns in a Layout.  I am trying with setting User Defined fields and setting them to the budgeted quantities through Global Change, However the data is not coming right, How do I do that?

Thanks

 

Pranab

2 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·

    Hi Schedulers,Can this not be

    Hi Schedulers,

    Can this not be done? Can we not have a layout with all resource assignment? Has someone designed such a layout?

    Thanks,

    Pranab

  2. 0
    Patricia Le Clainche ·

    Dear all,Did you try in

    Dear all,

    Did you try in Resources Assignments View ? It should be OK. You can filter for instance by Resource Type =Non Labor. You can add columns dealing with costs. On spreadsheet, you can select costs or units, per period (month, quarter...) or cumulative.

    Regards.

    Patricia