P6 8.2 PMDB Databse

Nitin ChauhanMember for 12 years 7 months
Created
2
2
0

Hi,

Can anyone please help me with any existing document; and any online locations where I can get details regarding the PMDB database.

 

What I precisely need is to get the name of table/field in PMDB database; for fields in P6 front end.

E.g:  Project Name is stored is projWBS table under wbs_Name field.

I have worked woth ODS schema; and started working in PMDB very recently; most of time get wasted in identifying the field in PMDB schema...

Any help is appreacited..

 

Regards

Nitin
 

2 replies

Oldest first
  1. 0
    Manochehr Hosseini ·

    Nitin, you can find all about

    Nitin,

     

    you can find all about PMDB schema in Documentation folder in installation CD, more over you can download them from oracle edelivery website.

     

    Regards,

    Manochehr 

  2. 0
    Sachin Gupta ·

    Nitin,You can look at the

    Nitin,

    You can look at the online document http://docs.oracle.com/cd/E25030_01/schema_documentation.htm

    Regards,
    Sachin Gupta

Log in or join to reply