Can anybody suggest me, how to upload huge numbers of activities (100000 or more) with predecessor-successor link, resources and other data directly from excel spreadsheet to Primavera P6? Can it be done directly, or there is any interfacing software to do it easily?

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Use the excel file through

    Use the excel file through SDK.
  2. 0
    Rangarajan Ramaswamy ·

    Ya SDK are the best when the

    Ya SDK are the best when the activities are too many.

     