Budgeted Man Hour
In the Open Standard
Vinod KumarMember for 12 years 7 months
- Created
- 2
- 1
0
Sir,
Please help me in the following issue.
Already I have a baseline schedule but due to some material delay i had to revise my schedule . As per the new dates already updated the activities but the budgeted manhours was not moving to new dates in activity usage spreadsheet.
Thanks and regards
VInod Kumar
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?