Budgeted Man Hour

Vinod KumarMember for 12 years 7 months
Created
2
1
0

Sir,

 

Please help me in the following issue.

 

Already I have a baseline schedule but due to some material delay i had to revise my schedule . As per the new dates already updated the activities but the budgeted manhours was not moving to new dates in activity usage spreadsheet.

 

Thanks and regards

 

VInod Kumar

2 replies

Oldest first
  1. 0
    Pranab Kumar Deb ·

    Vinod,What version of

    Vinod,

    What version of Primavera are you using? Did you right click on the Labor Units Section of the screen and select Spreadsheet Fields - Budgeted Labor Units?

    If yes, you may want to Try Assigning baseline again=Go to Project>Assign Baseline and assign baseline again. If this does not correct the problem, I need to know if the Remaining Quantity and Budgeted quantity are the same in the Activity Usage Spreadsheet.

    Thanks

  2. 0
    Ravi Katare ·

    Hi,Run a GC;If Planned

    Hi,

    Run a GC;

    If Planned start/finish is not equal to blank

    Then Planned start/finish equal to Start/Finish.

    What you have to do is replace planned start and planned finish with start and finish.

    - Ravi