Natasha,
Thats very easy stuff. Nothing much to worry about. Just follow me with the steps:-
Step 1. First for clarity add the following columns to your view
- Variance BL Project start date
- Variance BL Project finish date
Step 2. Next goto Filter -> New -> write filter Name as "Activities slipped from baseline"
Step 3. For filtering the activities that slipped from the baseline start date:-
Under the filter Parameter column -> Select Any of the following from the drop down -> Next adjacent to the Where row under Parameter column select Variance BL Project start date from the drop down -> under is column select is less than from the drop down - > in value column put 0d for filtering all the activites that slipped from baseline start date or in your case -5d for filtering all the activities that slipped more than 5days
Step 4. Now we are going to add one more condition for filtering the activities that have slipped from the Baseline finish date
Click Add -> Next adjacent to the newly created Or row under Parameter column select Variance BL Project Finish date from the drop down -> under is column select is less than from the drop down - > in value column put 0d for filtering all the activites that slipped from baseline finish date or in your case -5d for filtering all the activities that slipped more than 5days
Click OK -> Click OK again in Filter menu
Voila!!! You have all the activities that slipped from the Baseline start date and Baseline Finish date
You can refer to the Variance columns to check if the data filtered is correct or not and then you can remove the Variance columns
Also, to compare the schedule with the last baseline simply goto Project menu -> select Assign Baselines -> under Project Baseline -> select from the dropdown the last baseline that you want your schedule to be copmared with -> click OK -> apply the filter again -> Thats It done !
Regards,
Ranga