Suspend and Resume activities more than one time
In the Open Standard
Ibrahim MohammadMember for 12 years 6 months
- Created
- 6
- 2
0
Hi all,
The project I'm working on has been suspended for about 3 weeks. All at that time on-going activities were suspended. I used Suspend Date and Resume Date in Primavera P6 8.3 to record the Suspend and Resume dates for the affected activities. Later, the suspension was lifted.
Now, the project is suspended again. Some of the before suspended activities are suspended again, and other new activities also. This new suspension is still running.
How to record the new suspend and resume dates in easy and fast way in Primavera P6 8.3?