Skip to content

Resource Levelling

Siddiqui TquiMember for 13 years 11 months
Created
2
2
0

Dear All,

I have Created A programme in p6, resource is also loaded. some of the resources overloaded. i can see that in resourse usage profile. but i tried to level the resource using resource levelling wizard, but its not working. after resource levelling max unit per time should increase to accomodate the overallocated resource, but it not happening in my case. i have been trying to solve this from past two days plz help me.......

2 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi SiddiquiEfficient resource

    Hi Siddiqui

    Efficient resource leveling is not easy. If resources are overloaded, then you have not many options. The first one is to allow the end date of the project to move to allow the resources to be leveled. The second option is to increase the number of resources in the resource availability.  There are many options to level the resources but these are not easy and require fundamental knowledge of scheduling. 

    I have some articles on resource leveling  for beginning and junior planners on my website that can help you.

    www.plannenvoornietplanners.net

    Regards Johannes

  2. 0
    Ravi Katare ·

    HiCheck the duration type, It

    Hi

    Check the duration type, It should not be Fixed duration one

     

    - Ravi

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?