original duration become zero

Ferhat AciciMember for 13 years 10 months
Created
1
1
0

hi guys

After entering budgeted cost value to an activity, original duration shall become zero.whats the problem?

 

thnx

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    make sure that your project

    make sure that your project is open

    go to the projects directory

    make sure that your project is highlighted

    select view show on bottom 

    click on the defaults tab

    for the duration type change it to Fixed Durations & Units

    go back to the activities directory

    filter for ALL activities

    add a column for duration tpye

    on the top activity in the duration type column double click and select Fixed Durations & Units

    no do a fill down for the rest of the activities

    this should solve your problem

     

Log in or join to reply