Gannt chart showing logic between baseline activities

John WilsonMember for 15 years 11 months
Created
1
3
0

I am using P6.7 and have copied and pasted with a base line a very simple schedule, which seemed to work ok

When I view the current schedule with baseline and also the logic links the logic is between the baseline activities.

Has anyone seen it before and what was the solution

Rgds John

1 reply

Oldest first
  1. 0
    John Wilson ·

    Sorted it If the baseline bar

    Sorted it

    If the baseline bar has higher priority that the remaining bar the logic will go to the baseline activities

Log in or join to reply