Skip to content

Resource and activity date misalignments

Helen WardMember for 13 years 7 months
Created
1
1
0

Hi

Running a schedule of 30 projects, circa 50k activities with a large numver of interproject links.

At random times and on random activities I am seeing the resource dates either inside or outside of the activity Start and Finish dates.

Has anyone else experienced/resolved this please?

H.

1 reply

Oldest first
  1. 0
    Raymund de Laza ·

    Helen,Have to check if the

    Helen,

    Have to check if the Resource calendar is the same as Activity Calendar and as well as Default Calendar.

     

     

    Regards,

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?