Resource Duration Equal to Activity Duration

Eric PreisendanzMember for 12 years 8 months
Created
3
2
0

I created a cost loaded schedule. I did not do anything with the resource durations; when creating the schedule I just entered the duration in the activity duration column. I now need these activity durations to be copied into the resource durations without having to hand key in for all 2500 activities. I do not need the resource durations to change with the units, I just need the resource duration to always correspond with the respective activity duration.

Currently, all resource durations are 0 for non-progressed activities. Activities that have started display the actual activity duration

Let me know if you need any other info that would help out.

3 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Eric,See if the Resource

    Eric,

    See if the Resource Calendar is the same as the Activity Calendar and as well as the Default Calendar.

     

    Regards,

  2. 0
    Rowstone Fausto ·

    Good day Eric, Just make your

    Good day Eric,

     

    Just make your default unit/time  equal to 1 for all  assigned resourses. To make your activity duration equal to your budgeted units.

  3. 0
    Eric Preisendanz ·

    My units do not correspond to

    My units do not correspond to my duration. I have set up a $1 to 1 unit ratio. So an activity of $5000 would be 5000 units. But the duration is based on the predetermined duration of the activity. I need to transfer all of the activity durations to the resource durations (i.e.: Activity ID AA100: Duration = 5 days. all resources assigned to that activity need a resource duration = 5 days)


    Let me know if this is possible

Log in or join to reply