Disappearing Budget values

John RevereMember for 12 years 3 months
Created
5
1
0

The resource calendars are a mess and Im wondering if this is an issue as when an actual start date is entered to status the actvitiy the resource cost value is erased immediately? any ideas?

5 replies

Oldest first
  1. 0
    Jimmy Xie ·

    Dear JohnHow is your resource

    Dear John

    How is your resource "erased"exactly?

    Is it erased as 8 times less compare to the original budgeted unit?

  2. 0
    John Revere ·

    No it's not being reduced by

    No it's not being reduced by 8. It automatically disappears or changes to zero when you click on start date. I'm thinking when they setup P6 initially they must of clicked on a box to reset the values to zero. They have assigned resources and wonder if again there is a calculation setting that is causing the disappearance.
  3. 0
    John Revere ·

    The resource stays it's the

    The resource stays it's the budgeted value that changes to zero.
  4. 0
    John Revere ·

    The resources are not

    The resources are not disappearing it's the budget when you click on the actual start of an activity.
  5. 0
    Raymund de Laza ·

    Try to make changes of the

    Try to make changes of the "Duration Type"