Integrate GIS data into P6 schedule

Amir ShMember for 14 years 5 months
Created
1
1
0

Hi ,

Can you please advise me the best way for integrateing GIS data into P6 schedule, or visulaise the schedule on the poject Map based on GIS data?

 

Thanks

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Amir Shah,integrate GIS data

    Amir Shah,

    integrate GIS data into a P6 Schedule could be possible via custom fields; however P6 is not a time-location scheduling software as Tilos (www.tilos.org), and I doubt that you will be able to display both distance and time data together on a P6 schedule