How to equal actual labor units to earned value labor units in Primavera P6

Anton BroekzitterMember for 12 years 4 months
Created
4
2
0

Hi all,

I'm trying to make the actual labor units equal to the earned value labor units. I would like to do this either by global change or through export/import (excel).

I know I can do it manually, but that costs a lot of time. And I do understand, that once you press F9 it's all lost, so that why I want to do it through automated actions.

I have tried a few global changes, but it either ends in all errors or in all zero's. So please provide a step by step procedure.

I want to do this, so I can forecast how many units (hours) we need per week to complete the schedule. Where I would use the resource assignment calendar from Primavera.

Best regards,

Anton Broekzitter

4 replies

Oldest first
  1. 0
    Muhammed Anshad K ·

    bump

    bump

  2. 0
    Shaohua Chen ·

    when you have actual date ,

    when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .

  3. 0
    Shaohua Chen ·

    when you have actual date ,

    when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .

  4. 0
    Shaohua Chen ·

    when you have actual date ,

    when you have actual date , actual unit is equal to earned unit ,It is not possible to change againe after press F9.Did you use the resource curve ,maybe this curve will affect the result .