Unable to assign project code to activities

Robert McGheeMember for 18 years 6 months
Created
2
3
0

Have added a "project" code and when I go to Enterprise/Project Codes it shows up, but cannot find it on the list when I try to assign the code to an activity and have chosen the "Display: All Values."

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Robert, Project codes are

    Robert, Project codes are for projects and activity codes are for activities. Create activity codes to be assigned to an activity.
  2. 0
    Zoltan Palffy ·

    what you added are codes at

    what you added are codes at the project level NOT the activity level. To add codes at the activity level go to activities then select Enterprise then select activity codes.

    now you can assign the activities to these codes 