Original Durations incorrect
- Created
- 3
- 1
Hi,
Just wondering if someone can shed some light on a problem that has just popped up.
When we open any project in the sytem the orginal durations, (Group Sorted by WBS Levels) for the header is stating less days than it actually is.
It is not a user setting as it has happened to both of us in the office!
Example :
Duration = 51days
Calendar 1st July 14 to 22nd June 15
There is a level of effort activity that covers project management for the whole program with the same dates that shows the correct amount of dates.
Spoke to an experienced planner, who looked at the baselines / calendars etc and he couldn't come up with anything.
Any Ideas on how to fix this would be much appreciated.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?