Resource allocation for sub contractors

Paul ZachariaMember for 12 years 3 months
Created
3
2
0

Which resource type best suit for sub contractors in P6? Labour or Non Labour?? Normally, subcontractor prices are fixed unless there is any variation.

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi PaulI would set up a

    Hi Paul

    I would set up a generic labour resource for Sub-Con and re define it when the Sub-contract is let and the sub programme is integrated.

    Best regards

    Mike Testro

  2. 0
    Paul Zacharia ·

    Dear Mike Thanks for the

    Dear Mike Thanks for the reply.. Could you please explain further how you do it? Paul
  3. 0
    Dieter Wambach ·

    Paul It depends on your

    Paul

    It depends on your reporting requirements. It can be easier to separate own and subbies' resources by labour for the own and non-labour for the others. You can use labour for both and assign a resource code as well.

    Just try with a test project - multae viae Romam meunt. (Many streets going to Rome)

    The algorithms are the same for labour and for non-labour resources.

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?