Assign Weights to Entire Activity & WBS Summary Level

Irfan KhanMember for 17 years 3 months
Created
1
1
0

hi to all,

Here i am wondering a way to assign weights to my entire activities as well as WBS level.

My schedule is loaded with Man-hours but now my Client asking to show the weight on the schedule.

I have checked in P6 & there is no any default column i found where i am able to show the weights, but i guess by the help of UDF we can show those weightages.

any reply in regard will be highly appreciated.

 

Thanks in advance .... :)

1 reply

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Irfan   I'm not sure if I

    Hi Irfan

     

    I'm not sure if I understood right.

    Weight in P6 is given by budgeted units (labour or non-labour), material units or costs (labour, non-labour, material, expenses) or the sum.

    In the Activity Usage Profile you can easily create the s-curves. A better formatting would be in Excel or any other spreadsheet: Create a report in csv format --> read into Excel --> format the graphics --> print.

    If you'll need an explicite weight independent from budget (but why?) you can use a UDF.

    If you'll mark "Show Grand Totals" in Group&Sort iP6 will sum up. 

    Good luck with your planning

    Dieter 

     