Resource Lag & resource multiplication

Essam YassinMember for 12 years 9 months
Created
3
4
0

Hi, Every body 

How could i assign a resource with a certain lag for a particular activity ?

Then is there a way to make multiplications in resource assignment ( ex, to assign 3 workers for an activity , h repeat assignment trible which i believe it's ot practical ) ?

Thanks in advane

3 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Essam This is from the P6

    Hi Essam

    This is from the P6 Help:

    Original Lag (in the resource tab)

    The planned time lag between the activity's planned start date and the resource's planned start date on the activity. If the resource is planned to start work when the activity is planned to start, the planned lag is zero.

    You can assign a resource as often as you need - if allowed under project --> tab resources.

     

    Regards

    Dieter

  2. 0
    Essam Yassin ·

    Thanks WambachThe forst

    Thanks Wambach

    The forst question ( Resource lag ) i got it yasterday

    But for second one, i know that i can add whatever resource to an activity . My point is how to avoid clicking the same resource or role while assignment ? Specially that i add resources (Manpower ) by proffesion not by name ?

  3. 0
    Dieter Wambach ·

    Hi Essam i don't know a

    Hi Essam

    i don't know a multiplicator. You'll have to select twice , triple, ... The units are taken from the resource's default units

    For a choice by profession, study the chapter of the role concept in your reference manual.

    Regardss

    Dieter

Log in or join to reply