Shrink activity codes rows not relevant to an activity

Najam UddinMember for 12 years 1 month
Created
4
1
0

Hi,

When I group and sort activities by activity codes in the order; PHASE, EWP, CONTRACTOR and DISCIPLINE, there are 4 rows on top of activities for each code. If there is single activity and I assign it two codes PHASE and EWP, remaining two rows appear written as "No CONTRACTOR" and "No DISCIPLINE"

How to shrink those two rows so that only the relevant rows of codes appear on top of that activity. It will save at least two pages for me to print and schedule will look clean.

Regards

Najam

4 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Najam This is one of the

    Hi Najam

    This is one of the nasty elements of P6. In general I create a code value with a space or a period as name and assign the not assigned activities to it. Otherwise titles as "no discipline" are just confusing.

    Regards

    Dieter

  2. 0
    Najam Uddin ·

    Thanks Dieter. You mean we

    Thanks Dieter. You mean we can not shrink these rows?

    Najam

  3. 0
    Raymund de Laza ·

    Use the Filter to Hide the

    Use the Filter to Hide the Activities that have no Activity Codes

  4. 0
    Dieter Wambach ·

    Hi Najam If you group by only

    Hi Najam

    If you group by only one code you can filter and then use "Hide if empty". If you group by multiple codes, this will be difficult. By intelligent grouping you can reduce those "No Code...".

    Regards

    Dieter

Log in or join to reply