Resource Driven Activities vs Task Driven Activities & how it effects Original Duration

Richard HarrellMember for 12 years 1 month
Created
3
2
0

Can anyone tell me how P6 handles the original duration while an activity is Resource Driven vs Task Driven ?  The Activity Calander is 7x24x2 while the Resource Calander is 5x10x1.  

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi RichardNormally the

    Hi Richard

    Normally the resource driver over rides the task.

    This leads to all sorts of confusion if the two are out of sync - best keep them the same.

    Best regards

    Mike Testro

  2. 0
    Richard Harrell ·

    If an Activity is Task Driven

    If an Activity is Task Driven the Original Duration for that activity may be 4 as displayed in the original duration field.  Change the activity to Resource Driven and the original duration as displayed will change.  I know why it changes, but what I am trying to do is to get it to display the 4.  The client wants to see the "Activity Original Duration" not the "Resource Duration".  I have a very difficult time trying to write and explain what I am asking.  It is a big weakness.  If you can understand me, I would appreciate any help.  Thanks

  3. 0
    Richard Harrell ·

    Thanks Mike...

    Thanks Mike...