I have a project which I split into subprojects. 

Example 2 project are activity type projects and are just different disciplines but actually make up one project schedule. 

The 3rd project is a milestone schedule linked to the 2 activity schedules.

I would like to know if there is a way to make the milestone schedule have no weight on the performance % complete calulation for the 2 activity schedules?

 

if I open only the activty programs I get 20% complete, if i open all 3 I get 3% complete.

This does not make complete sense since the milestones don't even role up percent coplete into the wbs like the activity schedules do.

I understand it probably weighs down the progress simply because it adds weight to the schedules, being linked to them.

Is there a way for me to keep this structure, but remove the weighting of the milestones on the activity plans?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    you cant roll up percent

    you cant roll up percent completes becasue activities can have different percent complete TYPES

    this woudl be like compairing apples and oranges

    here is a link to my documentation expalinig this 

    http://pmsite.com/forums/viewthread/3068/