Skip to content

P6 V7.0 Resource Profile Editing

Michael ThompsonMember for 15 years 2 months
Created
3
2
0

Looking for some expert help.  I'm creating some resource profiles for various projects.  My problem is that using the profile within P6, the cumulative cost curve is in the same color as the vertical bars (using either budgeted or remaining early or late units).  The cumulative cost curve is hidden by the bars of the same color.  I don't see any way to change the color of the cumulative curve independently of the vertical bars.  Is there a solution to this within P6, or do I need to export to Excel?  Thanks in advance.

Mike Thompson

3 replies

Oldest first
  1. 0
    Ahmed Aziz ·

    Hi Thompson, On the resource

    Hi Thompson, On the resource profile window on the bottombright corner of the primavera screen, right click and chose tobedit the resource bars and then assign the color you want for the remaining and actuals. Aziz
  2. 0
    Ahmed Aziz ·

    Hi Thompson, On the resource

    Hi Thompson, On the resource profile window on the bottombright corner of the primavera screen, right click and chose tobedit the resource bars and then assign the color you want for the remaining and actuals. Aziz
  3. 0
    Zoltan Palffy ·

    in the lower right hand side

    in the lower right hand side graphics area right click and select Resource Usage Profile Options

    this is where you can change the colors of the histogram bars as well as the cumulative curves.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?