Actual Finish Date vs Percent Complete

Tom TomMember for 12 years 2 months
Created
7
2
0

Hello All,

    Is there a way to to claim the completion date for an activity without declaring it 100% complete. Everytime I check the finish date box Primavera automatically declare it 100%. 

7 replies

Oldest first
  1. 0
    Paul Harris ·

    If a task is finished it is

    If a task is finished it is 100% complete, if it is not finished it is not 100% complete and all scheduloing sofwtare works this way.

    You could use a User Defined Field or the Physical % Complete may be set at 100% with an Actual Start but no Actual Finish.

     

    Regards

    Paul E Harris
    BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
    Managing Director and President
    Eastwood Harris Pty Ltd, Australia

    http://www.eh.com.au,  http://www.primavera.com.auand http://eastwoodharris.com.

    Project Control Consultants and Planning and scheduling software book and training material publishers

    Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/

  2. 0
    Yanqing Gong ·

    Hello Tom,        you can use

    Hello Tom,

            you can use the "Physical % Complete" or "Activity % Complete", when you check the finish date box, the progress of these two columns will keep unchanged.

  3. 0
    Zoltan Palffy ·

    what you are asking to do is

    what you are asking to do is not logical look at your wording you want to "CLAIM" a completion date but you do not want to say that it is 100% complete. If it is NOT 100% complete then you cannot CLAIM a completion date. This is illogical. What you can do is say that the activity is 100% complete but NOT CLAIM a completion date.

    By definition what you are trying to do is not correct.

    Is there some reason why you want to do this ? Maybe you need to use suspend and resume or maybe you need to split the activity into 2 activities.

     

  4. 0
    Tom Tom ·

    The contract document allows

    The contract document allows us to claim actual complete date for certain activites without claiming 100% complete so as not to restrain successor activities. This is for activities completed but we can not bill 100%

  5. 0
    Zoltan Palffy ·

    Ah now you have point out the

    Ah now you have point out the real issue. What you are talking about is unlinking the physical progress from the costs for billing for activities.

    Go to the projects directory look at the calculations tab uncheck recalculate actual units when duration % complete changes 

  6. 0
    Tom Tom ·

    I tired that but it didnt do

    I tired that but it didnt do what I wanted. My EV calculation is based on Physical % complete

  7. 0
    Zoltan Palffy ·

    you can still give the

    you can still give the activity 100% complete and have an actual finish date but leave the cost at a vlaue less than the budgeted amount.