Skip to content

Duration changing with resource changes

Tom TomMember for 12 years 2 months
Created
1
2
0

Hello All,

     I am having trouble with my project duration changing everytime I change the max units/time of a rersource. What am  I doing wrong. I dont not want a resource to recalculate any of my durations.

Thanks

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    go to your project

    go to your project directory

    make sure that your project is highlighted and open

    look at the defaults setting look at the duration type change it to fixed duration & units. Now when you add new activites the resource will not drive the duraitons.

    now you have to fix the duraiton type for the existing activities

    go to activities add column

    look under General and add Duration Type

    change the top one to fixed duration & units then do a fill down for the remainder of the activities

    this should fix it.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?