How cost calculation can be changed from the starting date of the activity to finishing date

Paul ZachariaMember for 12 years 3 months
Created
1
3
0

Hi Guys,

I prepared a cash flow report by customizing the planned & cummulative planned calue. The project activities start in March 2014 and the last activities fall in Feb 2016. Whereas the cash flow shows values only till Jan 2016. The corresponding value for Feb 2016 is zero since there are no activities starting in Feb 2016. I need the cost to be calculated based on the finishing date of the activity. 

Can somebody suggest how to fix it.

 

 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    check your calendars and your

    check your calendars and your resource calendars take a look at smaller increments for your time scale maybe in weeks or days in the view.

    Also check your resource to see if drive activities dates by default is checked.

    Under the resource check you default units/time it should not be 1 or 0

Log in or join to reply