Primavera 6 - Autofilter Value

Muhammad AmmarMember for 19 years 8 months
Created
3
1
0

Hi all,

 

I will like to know, when you open filter dialogue box and create a new filter, there are "value" "highvalue fields"

Like in these fields, one can enter "specific date","DD+2W", CD+2M".

 

I would like to know any database or literature that can show P6 user, what could be possible range of inputs to high value fields like

 

DD+2HRS or ES+2d or etc

 

can anyone guide me where i can get this type of information, and same goes to field in global change.

 

Thanks.

Regards

Ammar

3 replies

Oldest first
  1. 0
    Muhammad Ammar ·

    ANYONE?

    ANYONE?

  2. 0
    Zoltan Palffy ·

    this can be Valid values must

    this can be 

    Valid values must be in the format "+4W" Where the '+' can be either '+' or '-', indicating future or past where the number is the number of hours/days/weeks/monthswhere the letter indicates (H)ours, (D)ays, (W)eeks, (M)onths or (Y)ears.

     

    there is not a standard answer because you can have codes or where their values can be within a range

    this is let to the users to decide how to use them 

  3. 0
    Muhammad Ammar ·

    Thanksyou zoltan.your help is

    Thanksyou zoltan.

    your help is appreciated :)