Total float zero but not on critical path.

Gün GöksuMember for 21 years 6 months
Created
4
4
0

Hi everyone,

I have a schedule where all dates are entered in days. This is shared on a live server.

I somehow now have a schedule with some activities having a total float of above zero but less than 1.

 

As a result, on a reset to default F9, some activities show zero float but not critical.

 

I know of a hundred ways to show these as critical, however, I would like the default settings to show this without any tinkering.

How you would approach debuging these less that 1 day floats?

 

notable hints are: Floats with 0.11 or 0.10 values, calendars with 9h/d, 5d/w and 10h/d, 7d/w etc.

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    go to your Projects directory

    go to your Projects directory click on the settings tab

    under Define Critical Activities

    check Total Float less than or equal to

    then on the right hand side put in the number 1 or 0 which ever you prefer

  2. 0
    Gün Göksu ·

    Thanks Zoltan for the reply.

    Thanks Zoltan for the reply. :)

    I have no problems showing these as critical,

    I am looking for info on how to tackle the root reason this 0.11-0.10 float is created.

    what is the bit of data that causes this.

    Thanks again.

  3. 0
    Gün Göksu ·

    Thanks Zoltan for the reply.

    Thanks Zoltan for the reply. :)

    I have no problems showing these as critical,

    I am looking for info on how to tackle the root reason this 0.11-0.10 float is created.

    what is the bit of data that causes this.

    Thanks again.

  4. 0
    Zoltan Palffy ·

    without looking at it I would

    without looking at it I would say that some of your durations are not in whole days turn on the decimals in the durations

    to check this look under edit users preference.

    Then click on the Time Units tab on the left 

    under the Durations format on the right choose 2 decimals

    also your data date TIME and or your Project Must finish by TIME maybe in correct

    and your calendar may not be in whole hours.

    also if you have any hard constrained dates their TIMES could be incorrect 

    to check this go to edit users preference 

    click on the Dates tab on the left and at the bottom select TIME then check 12 hour

Log in or join to reply