Resource hours

Gordon BennettMember for 22 years 11 months
Created
1
2
0

I have just started on a project. When I review Budgeted resource hours on the activity they are 8 times higher that what the other planner sees. How do I resolve ?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    Sometimes this happes when

    Sometimes this happes when you convert a p3 project to p6 

    1. check your resource default units/time it would be 8

    to fix this run a global change 

    where budgeted units is greater than 8 then 

    budget units equals budget units / 8

Log in or join to reply