Remaining Units / Time
In the Open Standard
Tanveer Ahmad NiaziMember for 20 years 10 months
- Created
- 3
- 1
0
Hi,
I am working on resource loading in my programme (P6 r7), I have completed almost 25% of the activities untill yesterday, but today when i started plugging in the budgeted units (matetrial), I am not getting the "Remaining Units / Time". I have also tried by plug in the units in the Remaing Units / Time and still I am not getting the Budgeted Units.
- I also tried Checked and Check off "Drive Activity Dates by Default" in the general tab of Projects and the resource assignment.
I am not convinient in import / export to/from Excel. Please advise me
Cheers
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?