Remaining Units / Time

Tanveer Ahmad NiaziMember for 20 years 10 months
Created
3
1
0
Hi,
I am working on resource loading in my programme (P6 r7), I have completed almost 25% of the activities untill yesterday, but today when i started plugging in the budgeted units (matetrial), I am not getting the "Remaining Units / Time". I have also tried by plug in the units in the Remaing Units / Time and still I am not getting the Budgeted Units.
- I also tried Checked and Check off "Drive Activity Dates by Default" in the general tab of Projects and the resource assignment.
I am not convinient in import / export to/from Excel. Please advise me
Cheers
 
 
 
 
 
 
 
 
 
 
 

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    what is your default

    what is your default units/time  ?

  2. 0
    Tanveer Ahmad Niazi ·

    Hi,My default unit is

    Hi,

    My default unit is Budgeted Units

  3. 0
    Zoltan Palffy ·

    this must be a number 8 ? 10

    this must be a number 8 ? 10  ? 12 ?

Log in or join to reply