Level of effort activity

Essam YassinMember for 12 years 9 months
Created
3
1
0

Dear All ,

 

While loading a cost for my project , i tried to assign the resources for general activities ( e.g. Indirect manpower cost or laydown cost ) to a " Level of effort activity " .

But while updating those LOE activities, i observed that there are no Earned value calculations for those activities .

Is there any way to fix this problem or this is an attribute to LOE activity?

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    LOE Activities only measure

    LOE Activities only measure schedule performance as it relates to time no actual work effort.

    Using a LOE to calculate earned value distorts the total project EVM becasue the values derived from LOE grows relative to the total project planned value

    LOE does not distinguish cost variance from schedule variance. All variance is recognized as cost variance for LOE work
  2. 0
    Essam Yassin ·

    Well , so how i can assign

    Well , so how i can assign such reourced ( eg. indirect manpower ) to an activity ??

  3. 0
    Zoltan Palffy ·

    you can still put indirect

    you can still put indirect manpower on it 

Log in or join to reply