Update Progres in Primavera incorrectly completes activities

Charlie DanielsMember for 12 years 10 months
Created
3
2
0

Hi,

 

I have been struggling with this problem for some time now and have not managed to resolve it.

It is a fairly large program so it would be useful to find the solution to my problem.

I usually review the activities and update each one with the reported progress and status.

Once I have done this I want to progress the the data date.

I go to tool update progress and select the new data date and apply.

The project is updated.

BUT!

some activities have which should not be have been changed to completed.

I have to do a manual exercise each time to put it back in progress and apply the correct percentage and finish dates.

This is an unecessary time consuming exercise.

 

Any suggestions?

3 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi CharlieWhen you have

    Hi Charlie

    When you have manually updated the activities then just set the new data date and hit F9 and schedule . Do not use the Tools> update button because this funtionallity is used for updating a schedule whereby all the activities are updated as they are progressing as planned. This is not always the case. 

    Trust this helps

    Johannes

  2. 0
    Charlie Daniels ·

    Hi Johannes, Thanks for the

    Hi Johannes,

     

    Thanks for the reply, yes it is very helpful. ;-)

     

    Regards

    Charlie

  3. 0
    Zoltan Palffy ·

    Primavera is updating it

    Primavera is updating it correctly but it is you who is using the tool incorrectly.

    that is not the correct way to update 

    1. Determine what your new data will be You can only show actual start and or finishes unto that date 

    2. progress each activity by putting in the date that it actually started and any remaining duration to finish this activity. If the activity is done then also put in the actual finish date.

    3. Press F9

    4. Change the data date

     

    Never use update progress becasue that assumes that everthing actualy started and finished as originally planned and we al know that NEVER happens.

Log in or join to reply