How to remove symbols (*, A) from Dates
In the Open Standard
Nicolò SpagnaMember for 11 years 10 months
- Created
- 4
- 2
0
Hello everyone,
when I creat a report in order to extract the Finish Dates of the Activity IDs and put them in an excel database, activities that are in progress or performed, will be extract in this way:
| PRC-3000/010 | Completed | 01-09-14 A | 15-09-14 A |
Activities with constraints, will instead appear in this way:
| PRC-3010/030 | Not Started | 10/11/2014 | 11-06-15* |
Is that possible to remove these letters/codes in order to have always the same layout of the data?
This is how I would like they all appear:
| PRC-3000/030 | Not Started | 19/11/2014 | 07/07/2015 |
| PRC-3000/040 | Not Started | 08/07/2015 | 29/08/2015 |
Thanks in advance!
Ciao
Nicolò
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?